“Value Engineering” — Four Case Histories

- Organization:
- Deep Foundations Institute
- Pages:
- 4
- File Size:
- 1656 KB
- Publication Date:
- Jan 1, 2003
Abstract
"Case 2. 100th Street Bus Depot: Elimination of Deep Caissons in Favor of Spread FootingsThe PROJECTThe 100th Street Bus Depot is a new five-story bus terminal for the New York City Metropolitan Transit Authority occupying one city block in Manhattan between 99th and 100th Streets, and between Lexington and Park Avenues. It replaces a former two-story garage, built in the 1890’s and initially used as a trolley-car barn. The new structure is a steelframed building with concrete floors and includes a partial basement near its middle. The easternmost column line with design loads of 10 MN (1,125 tons) is within 1.5 m of the underlying multi-tube Lexington Avenue subway system. To support the new columns along the subway line, the project bid plans had called for 1 m diameter and 17 m deep drilled shafts. The upper 14 m of each unit would have required 50 mm separation from the surrounding rock to prevent stress from being imposed on the roof and walls of the adjacent tunnel. The column loads were thus transferred to below the base of the tunnel and supported by 3 m long sockets in bedrock. The bid documents contained extensive test boring information, which revealed that the project site was underlain by massive Manhattan Mica Schist bedrock within just 3 m below street level. In fact, the Lexington Avenue two-level and multi-tube subway had been tunneled through this rock circa 1910, leaving an about 6 m thick solid roof over the upper-level subway. The NX rock core recovery values were near 100 %, with average RQD of 75 %.The CHANGEThe Bus Depot project was let as a design/build contract with a very aggressive fast-track schedule. Both the pre-bid preliminary design and the subsequent final design by the Contractor’s own hired design engineers relied heavily on very restrictive codes, including unnecessarily conservative approaches to seismic design. Any suggestion for value engineering change was undesirable and was strongly resisted. Yet, objecting against the blind reliance on codes in foundation design, the author questioned the real need for the deep drilled shafts to support the columns along the subway. The unsupported statement that no stresses from the new structure can be imposed on the roof and walls of the adjacent tunnel was not sufficient reason for the drilled-shaft design. Unconvinced that deep shafts were necessary, the author rushed to MTA’s warehouse where many rows of rock core boxes were neatly stacked. Careful inspection and some simple testing of the rock cores with the blows of a geologic hammer gave support to the reservations about the design. Later, as expected, the schist bedrock at this site was found to be hard to very hard with unconfined compressive strength values estimated to range from at least 70 MPa to over 100 MPa (10,000 psi to 15,000 psi). The tensile strength of the rock was assessed to be minimum 5 MPa (750 psi)."
Citation
APA:
(2003) “Value Engineering” — Four Case HistoriesMLA: “Value Engineering” — Four Case Histories. Deep Foundations Institute, 2003.