Results of geologic investigations, in-mine instrumentation, and numerical modeling are presented for two longwall mines in which pillars with large width-to-height ratios (8 to 9) are used. These investigations revealed that wide pillars unload when subjected to sufficient stress and that pillar unloading is influenced by geologic conditions. Field measurements in mine 1 clearly indicated load transfer from the longwall area toward the gate roads, resulting in pillar failure near the margin of a fluvial channel. Loads were shown to transfer to a harrier pillar (width height ratio equal to 9), contributing to progressive failure of this pillar. Unloading of the barrier pillar was associated with significant load transfer to the two-seam submains to the north of the harrier, contributing to roof falls, floor heave, and rib spalling within the submains. Stress analysis results addressed pillar peak strength and unloading behavior that was in agreement with the measurements and underground observations. Underground observations and stress analyses were completed before and after longwall mining near a six-entry submain in mine 2. This submain was intended to he used as a temporary bleeder and tailgate for a small longwall block consisting of one to two panels, depending on the development schedule in other areas of the trine and observed ground conditions. Numerical modeling using both elastic and inelastic pillar behavior for submain pillars with a width-to-height ratio of 8 was completed before mining began. Results indicated that pillar unloading was likely. During retreat of the first longwall panel, pillars unloaded. as evidenced by progressive rib spalling along the cleats, This behavior was mostly confined to the immediate face area, an observation that was in agreement with the modeling results,
Full Article Download:
(1803 kb)


Additional chapters/articles from the SME-ICGCM book Proceedings 19th International Conference On Ground Control In Mining

An Approach To Identifying Geological Properties From Roof B
Field Experience Of Measuring The Acoustic Energy From A Ham
Advancements In Reflective Seismic Tomography For The Locati
Longwall Geomechanics, An Australian Perspective
Moonee Colliery: Renewing The Economic Viability Of A Mine U
Successful Application Of Hydraulic Fracturing To Control Wi
Pillar Mining And Longwalling Below Massive Roof Strata: Geo
High Capacity Tensioned Cable Bolts For Tailgate Support
Single Point And Full Scale Laboratory Testing Of Timber Cho
Optimizing Secondary Roof Support With The NIOSH Support Tec
The Use Of Cribless Tailgates In Longwall Extraction
Five Stress Factors Conducive To Bumps In Utah, USA, Coal Mi
Development Of Stress Measurement Techniques In Bump-Prone C
Coal Mine Seismicity And Bumps: Historical Case Studies And
Multi-Scale Assessment Of Coal And Gas Outbursts Based On Fr
Horizontal Stress: The Root Of All Evil?
Utilizing The ?Advance And Relieve? Method To Reduce Horizon
Regional Horizontal Surface Displacements Due To Mining Bene
Prognosis And Control Of Mining Induced Surface Subsidence A
Prediction Of Subsurface Subsidence For Longwall Mining Oper
Development Of A Statistical Technique For Assessing Sandsto
Evaluation Of Surface Subsidence Potential Along A Pipeline
Roof Monitoring In Limestone Mines-Experience With The Roof
Site Characterization For Planning Underground Stone Mines
Potential Problems Related To Mining Under Or Adjacent To Fl
Mine Planning For Longwall And Pillar Retreat Panels Subject
Optimization Of District-Wide Mine Layout In Multi-Seam Mini
Application Of Bolt Design Criteria At Galatia Mine
The Utilization Of Rockbolting Technology And Monitoring Tec
Rockbolting For Highly Stressed Roadways
Evaluation Of Measurement System For Monitoring The Stabilit
Quality Management For Grouted Rockbolts
Evaluating Anchorage Mechanisms Of Fully Encapsulated Rock B
INSTáL CableOx: A New Tensionable & Corrosion Resistant Cabl
Rock Reinforcement Longevity
Progress In The Development Of A Roof Bolt Design Methodolog
Case Studies Of Progressive Pillar Failure In Two Mines Usin
Jointing Effects On Pillar Strength
Impact Of Vertical Stress On Roadway Conditions At Dartbrook
Stepwise Support Technology For Extremely Soft Rock Roadway
Mobile Roof Supports For Pillar Retreat Mining
Three-Dimensional Simulations Of The Roof Behavior In Coal R
Roof Behavior In South African Coal Room And Pillar Panels
Extended Cut Out Distances In Continuous Miner Sections In S
Roof Control Analysis In North River Mine
Analysis Of The Seam Inclination Effect On Roof Stability
The Application Of Rock Mass Classification Principles To Co
Mining Geotechnical Benchmarking
Using The Point Load Test To Determine The Uniaxial Compress
The Influence Of Water Content On Strength Characteristic Of
Polymer Membrane Liners In Underground Coal Mines - Ground C
Applications Of Cement Grouting Method For Controlling Weak
Analysis Of Safety Aspects And Mining Practices For Effectiv