I-470 Mine Remediation

Gallagher, Sheryl D.
Organization: Deep Foundations Institute
Pages: 6
Publication Date: Jan 1, 2009
The project consisted of filling an abandoned underground limestone mine to facilitate construction of a new entrance ramp to I-470 in Lee?s Summit, Missouri. Due to collapse of mined areas near the project site, design included determination of the limits of remediation for the project and minimum construction requirements for mine infilling. The Judy Company, contractor selected for the mine infilling, experimented in the laboratory with several grout mixes to determine the appropriate mix for the project. Infilling was accomplished from the ground surface, and camera observation was used to monitor the barrier wall construction and infilling process. It was discovered that some of the mapped rooms were larger and some were smaller than indicated on the construction plan.
Full Article Download:
(281 kb)