Tertiary Grinding Circuit Installation at Chino Mines Company

Vanderbeek, James L.
Organization: Society for Mining, Metallurgy & Exploration
Pages: 8
Publication Date: Jan 1, 1998
The Chino concentrator commenced operation in 1982 as a SAG-ball mill circuit which could process 37,500 stpd of ore. Since 1982, a series of process improvements such as the addition of two stages of SAG recycle crushing, allowed throughputs to increase to more than 48,000 stpd, at the expense of significantly coarser flotation feed sizing and reduced recovery. To compensate a third (tertiary) stage of grinding consisting of four 1250 hp Vertimills was installed which has allowed the flotation feed size and recovery to return to historical levels. The design and operational characteristics of the Tertiary Grinding Circuit are described.
Full Article Download:
(281 kb)