Gallery Towers, Melbourne: Successful Approach To Difficult Piling Contract Management

Aiezza, Mario
Organization: Deep Foundations Institute
Pages: 8
Publication Date: Jan 1, 2002
This paper outlines the results of a relationship developed during the design and construction of the foundations for the Gallery Towers project in Melbourne. Both the builder and the piling contractor were determined to arrive at a satisfactory foundation solution to the problems encountered at the site. The scope of piling work was to provide load-bearing piles under the building columns, some of which were located within a retention system that also required a piling solution. Geological conditions were variable and challenging. The site area was small and located adjacent to the National Arts Centre in the developed Southbank area, a high density office area. This presented logistical problems in limiting construction traffic on site and also demanding minimal noise and vibration emanating from piling activities. The piling contractor, Vibro-Pile, and the builder, Walter Construction Group, faced the challenges presented with a refreshing cooperative attitude that was beneficial to both companies. Commercial issues rising from design and construction problems were first put apart in order to allow the respective technical department of each company to work with minimum constraints to achieve the most cost effective solution. In the process usual adversarial attitudes resulting in loss of time and money was avoided. A number of issues were addressed successfully at minimum cost and time during this contract. Despite the difficulties encountered, the job was completed on time and with negligible claims for extras, resulting in the development of a strong mutual respect between both companies.
Full Article Download:
(281 kb)