Rock Socket Piles In The Sherwood Sandstone Of Central Birmingham

Whitworth, L. J.
Organization: Deep Foundations Institute
Pages: 8
Publication Date: Jan 1, 1989
Five trial piles were constructed during the trial pile programme for the Birmingham International Convention Centre. In addition, trial piles have been tested on two other sites in central Birmingham. Methods of pile construction were conventional sandstone rock sockets, sleeved piles and voided piles. The results of these load tests are compared with the theoretical predicted behaviour based on the results of unconfined compressive tests of rock core taken on the Convention Centre site and on other sites in the central Birmingham area. On the basis of this work, the various design procedures are discussed.